Managing Parallel Run Periods During ERP Migration for Risk Reduction

Learn how to plan, execute, and validate parallel run periods in ERP migrations to minimize data discrepancies, operational downtime, and financial risk during cutover.

9 min readSysGenPro Editorial
Managing Parallel Run Periods During ERP Migration for Risk Reduction

What is a Parallel Run Period in ERP Migration?

A parallel run period is a critical phase in ERP migration where both the legacy system and the new ERP system operate simultaneously for a defined duration. This approach allows organizations to validate data integrity, process accuracy, and system performance before fully decommissioning the old system. The primary goal is to reduce risk by identifying discrepancies in financial reporting, operational workflows, and integration stability while maintaining business continuity. Key risks to control during this phase include data loss, transactional mismatches, user confusion, and integration failures. By carefully managing the parallel run, organizations can ensure that the new ERP system meets business requirements and is ready for full production use.

Planning the Parallel Run Strategy

Effective planning is the foundation of a successful parallel run. The strategy must define the scope, duration, and specific business processes to be tested. Not all modules need to run in parallel simultaneously; a phased approach may be more practical. For example, finance and inventory modules might be prioritized due to their high impact on reporting and operations. The planning phase should involve key stakeholders from IT, finance, operations, and project management to align on objectives and success criteria.

Defining Scope and Duration

The scope of the parallel run should be tailored to the complexity of the migration and the criticality of the business processes. A typical parallel run lasts between two and four weeks, but this can vary based on the organization's size and the number of modules involved. The duration must be long enough to cover at least one full business cycle, including month-end or quarter-end closing processes, to validate financial reporting accuracy. It is essential to document the specific transactions and processes that will be executed in both systems to ensure comprehensive coverage.

Assigning Roles and Responsibilities

Clear role assignment is crucial to avoid confusion and ensure accountability. The IT team is responsible for system configuration, data synchronization, and technical support. The finance team oversees data reconciliation and financial reporting validation. Operations teams execute business processes in both systems and report any discrepancies. The project manager coordinates activities, tracks issues, and makes go/no-go decisions. Establishing a dedicated parallel run team with defined communication channels helps streamline issue resolution and maintain momentum.

Data Reconciliation and Validation

Data reconciliation is the core activity during a parallel run. It involves comparing data between the legacy and new ERP systems to ensure accuracy and consistency. This process includes validating master data, transactional data, and financial statements. Discrepancies must be identified, analyzed, and resolved before proceeding to the next phase. Automated reconciliation tools can significantly reduce the time and effort required for this task, but manual verification is often necessary for complex or high-value transactions.

Master Data and Transactional Data Checks

Master data, such as customer, vendor, and item records, must be consistent across both systems. Any discrepancies in master data can lead to downstream errors in transactions and reporting. Transactional data, including sales orders, purchase orders, and invoices, should be compared to ensure that all transactions are recorded accurately in both systems. This involves checking for missing, duplicate, or altered transactions. A detailed reconciliation report should be generated to document the results and highlight any issues that need attention.

Financial Reporting Validation

Financial reporting validation is a critical component of the parallel run. The new ERP system must produce financial statements that match those from the legacy system, within an acceptable tolerance. This includes balance sheets, income statements, and cash flow statements. Any variances must be investigated and resolved to ensure that the new system can support accurate financial reporting. This step is particularly important for organizations with strict regulatory or audit requirements.

Testing Integrations and Customizations

ERP systems rarely operate in isolation; they are integrated with other business applications and often include custom modules or workflows. During the parallel run, these integrations and customizations must be thoroughly tested to ensure they function correctly in the new environment. This includes validating data flows, API connections, and custom business logic. Any issues with integrations or customizations can disrupt business processes and must be addressed before cutover.

Integration Stability and Data Flows

Integration testing during the parallel run focuses on ensuring that data flows between the new ERP and other systems are stable and accurate. This includes testing real-time and batch integrations, monitoring for errors or delays, and validating data transformation rules. Any integration failures must be documented and resolved. It is also important to test error handling and retry mechanisms to ensure that the system can recover from transient issues without data loss.

Custom Module and Workflow Validation

Custom modules and workflows must be validated to ensure they meet business requirements and function correctly in the new ERP environment. This includes testing custom fields, reports, and business rules. Any discrepancies in custom functionality must be identified and resolved. It is also important to ensure that custom modules are compatible with the new ERP version and that any deprecated features are replaced or removed.

Managing User Adoption and Training

User adoption is a critical factor in the success of an ERP migration. During the parallel run, users must be trained on the new system and encouraged to use it for their daily tasks. This helps identify usability issues and ensures that users are comfortable with the new workflows. Training should be tailored to different user roles and should include hands-on exercises and troubleshooting guidance. Regular feedback sessions with users can help identify areas for improvement and address concerns.

Training Programs and Support

A comprehensive training program is essential to support user adoption during the parallel run. This includes initial training sessions, refresher courses, and on-demand support. Training materials should be updated to reflect any changes made during the parallel run. A dedicated support team should be available to assist users with questions and issues. This helps build confidence in the new system and reduces resistance to change.

Feedback and Continuous Improvement

Collecting feedback from users during the parallel run is crucial for continuous improvement. This can be done through surveys, focus groups, and one-on-one interviews. Feedback should be analyzed to identify common issues and areas for improvement. Changes should be implemented and communicated to users to demonstrate that their input is valued. This iterative approach helps refine the system and enhance user satisfaction.

Defining Go/No-Go Criteria

Clear go/no-go criteria are essential to make informed decisions about proceeding to cutover. These criteria should be defined at the beginning of the parallel run and agreed upon by all stakeholders. They should include measurable metrics such as data reconciliation accuracy, integration stability, and user adoption rates. If the criteria are not met, the parallel run should be extended or additional remediation steps should be taken.

Measurable Success Metrics

Success metrics should be specific, measurable, achievable, relevant, and time-bound (SMART). Examples include a data reconciliation accuracy rate of 99.5%, zero critical integration errors, and 90% user adoption rate. These metrics should be tracked throughout the parallel run and reported to stakeholders. If any metric falls below the threshold, a root cause analysis should be performed to identify and address the underlying issues.

Decision-Making Process

The go/no-go decision should be made by a cross-functional team including IT, finance, operations, and project management. The decision should be based on the success metrics and any outstanding issues. If the decision is to proceed, a detailed cutover plan should be finalized. If the decision is to delay, a remediation plan should be developed to address the issues and extend the parallel run. Clear communication of the decision and rationale is essential to maintain stakeholder confidence.

Rollback and Recovery Planning

A robust rollback and recovery plan is essential to mitigate risks during the parallel run and cutover. The plan should define the conditions under which a rollback will be triggered, the steps to execute the rollback, and the responsibilities of each team member. Regular testing of the rollback plan is recommended to ensure its effectiveness. A well-prepared rollback plan provides a safety net in case of unexpected issues and helps maintain business continuity.

Rollback Triggers and Procedures

Rollback triggers should be defined based on critical issues that cannot be resolved within a specified timeframe. Examples include data loss, system downtime exceeding a certain threshold, or critical integration failures. The rollback procedures should be documented and tested. They should include steps to restore the legacy system, revert data changes, and communicate the rollback to stakeholders. Regular drills of the rollback plan help ensure that the team is prepared to execute it efficiently.

Recovery and Post-Rollback Actions

After a rollback, a recovery plan should be executed to address the root causes of the issues and prepare for a retry. This includes analyzing the issues, implementing fixes, and re-testing the system. Communication with stakeholders is essential to manage expectations and maintain trust. The recovery plan should also include steps to update the parallel run strategy and go/no-go criteria based on the lessons learned.

Post-Parallel Run Stabilization

After the parallel run and cutover, a stabilization phase is essential to ensure the new ERP system operates smoothly. This phase involves monitoring system performance, resolving any remaining issues, and providing ongoing support to users. The stabilization phase helps identify and address any latent issues that may not have been detected during the parallel run. It also provides an opportunity to optimize the system and enhance user experience.

Monitoring and Issue Resolution

Continuous monitoring of the new ERP system is essential during the stabilization phase. This includes monitoring system performance, integration stability, and user activity. Any issues should be logged, prioritized, and resolved promptly. A dedicated support team should be available to assist users and address technical issues. Regular reporting on system health and issue resolution helps maintain stakeholder confidence.

Optimization and Continuous Improvement

The stabilization phase is also an opportunity to optimize the new ERP system. This includes fine-tuning configurations, improving performance, and enhancing user experience. Feedback from users should be collected and analyzed to identify areas for improvement. Continuous improvement initiatives should be implemented to ensure that the system evolves to meet changing business needs. This ongoing process helps maximize the value of the ERP investment.

Written by
SysGenPro Editorial

SysGenPro Editorial

Platform & solutions team

Practical guidance on ERP, AI automation, cloud deployment and enterprise transformation from the SysGenPro team.

Share this article

Frequently asked questions

Common questions on this topic. Talk to our team for anything specific to your business.

01What is the typical duration of an ERP parallel run?

The duration varies based on complexity, but typically ranges from two to four weeks. It should cover at least one full business cycle, including month-end closing, to validate financial reporting.

02How do you handle data discrepancies during a parallel run?

Discrepancies are identified through reconciliation, analyzed for root cause, and resolved by correcting data in the new system or adjusting the migration process. Critical discrepancies must be resolved before cutover.

03Is a parallel run necessary for all ERP migrations?

While not mandatory for all migrations, a parallel run is highly recommended for complex migrations or those involving critical business processes. It significantly reduces risk and ensures data integrity.

04What are the main risks of skipping a parallel run?

Skipping a parallel run increases the risk of data loss, operational disruptions, financial reporting errors, and user resistance. It can lead to costly post-go-live issues and delays in realizing business benefits.

05How do you measure success during a parallel run?

Success is measured using predefined metrics such as data reconciliation accuracy, integration stability, user adoption rates, and financial reporting consistency. These metrics should be tracked and reported regularly.

06Who is responsible for data reconciliation during migration?

Data reconciliation is typically a joint responsibility of the IT and finance teams. IT handles technical data comparison, while finance validates financial data and reporting. A dedicated parallel run team coordinates the effort.

Continue learning
View all articles
Explore the platform

Where to go next

Browse the knowledge hub

See how SysGenPro fits your business

Discuss your workflows, modules and deployment options with our team.

Back to resources